The installation and commissioning of Kazakhstan 3×8600kw Kaplan steam turbine was completed.
1.Flow rate: 195 m³/sec?
2. Water head: 16m
3. Installed capacity: 25.8 MW
4.Frequency: 50HZ
5. Voltage: 6.3KV
6. On grid
7. Outdoor transmission high voltage: 110KV
8.Elevation: 685 m
Next, we are designing the next 2×5MW Francis turbine project for investors.
Thank customers for their trust in FORSTER HYDRO. As a manufacturer of hydropower equipment, we will continue to create greater value for our customers.